2011 Larimer County Chip Seal Schedule
|
Construction Notes
|
Chip Seal Hot Line 970.498.5666
|
|
Location (Work is scheduled in order listed) |
Started Complete |
|||||||
|
1.
Meadow Heights |
July 12 |
July 20 |
||||||
|
2.
LCR 36 east of Timberline (approx. 0.4 mile between
city limits) |
July 12 |
July 21 |
||||||
|
3.
LCR 3F from LCR 36 north to Harmony Road |
July 13 |
July 21 |
||||||
|
4.
LCR 32E from LCR 3 (Poudre Bridge) east to LCR 901
(County Line) |
July 13 |
July 21 |
||||||
|
5.
LCR 901 from SH 392 north to LCR 32E |
July 13 |
July 21 |
||||||
|
6.
Mountain Range Shadows |
July 18 |
July 26 |
||||||
|
7.
LCR 30 from US-287 (College Ave.) east to LCR 13 |
July 21 |
July 25 |
||||||
|
8.
Turman Acres |
July 25 |
July 28 |
||||||
|
9.
Manor Ridge Estates |
July 25 |
Aug 18 |
||||||
|
10. Colland Center |
July 26 |
Aug 5 |
||||||
|
11. Victoria Estates |
Aug 1 |
Aug 5 |
||||||
|
12. LCR 19 from LCR 28 (57th
Street) north to Coyote Ridge (FC city limits) |
Aug 2 |
Aug 15 |
||||||
|
13. Taft Canyon |
Aug 3 |
Aug 15 |
||||||
|
14. Springfield Sub. |
Aug 4 |
Aug 18 |
||||||
|
15.
Springfield PUD |
Aug 4 |
|||||||
|
16. Imperial Estates |
Aug 8 |
Aug 18 |
||||||
|
17. Fox Hills PUD |
Aug 16 |
Aug 22 |
||||||
|
18. Wild Flower Ridge PUD |
Aug 16 |
Aug 22 |
||||||
|
19. LCR 38E from Masonville (LCR 27) east
to Bridge Project at LCR 25E |
Aug 09 |
Aug 16 |
||||||
|
20. LCR 38E from Bridge Project at LCR
25E east to LCR 19 (South Taft Ave.) |
Aug 10 |
Aug 19 |
||||||
|
|
|
|||||||
2011 Seal Coat Schedule (Watch for signs with dates for the work)
|
Locations |
Start |
Complete |
|
LCR 3 from LCR
32E to SH-392 |
July 11 |
July 15 |
|
LCR 36 (Kechter
Road) at LCR 7 (Strauss Cabin) |
July 7 |
July 15 |
|
LCR 5 from LCR
34C to Harmony Road (Poudre Bridge) |
July 7 |
July 15 |
|
LCR 32E from LCR
5 east to Poudre Bridge (east of LCR 3) |
July 11 |
July 15 |
|
LCR 36 east of
I-25 to LCR 5 |
July 12 |
July 18 |
|
LCR 30 from I-25
west to LCR 13 |
July 14 |
July 22 |
|
LCR 11 from LCR
30 to Carpenter Road (SH 392) |
July 18 |
July22 |
|
LCR 34 (Trilby)
at LCR 11 (Timberline) from Lemay to Timberline & south on Timberline
from Trilby for about ¼ mile |
Aug 23 |
|
|
LCR 25G
(Shoreline Dr.) |
July 20 |
July 22 |
|
LCR 17 between
Loveland and Fort Collins (1/2 mile only) at Fort Collins end |
July 6 |
July 9 |
|
LCR 17 south of
LCR 16 to second bridge |
July 6 |
July 9 |
|
LCR 23 and LCR 6
south of LCR 8 |
July 21 |
July 25 |
|
LCR 31 around Carter
Lake from LCR 8E to the Wind Jammer |
July 11-13 |
July 15 |
|
LCR 29 just
north of LCR 20 |
July 7 |
July 9 |
|
LCR 13 from LCR
30 north to SH 392 |
July 19 |
July 22 |
|
LCR 38E ( a
short section near LCR 25E) |
July 21 |
July 24 |
|
Taft Canyon |
Aug 24 |
|
The Larimer County Road and Bridge Department begins their 2011 Seal Coat Program on or about July 6th. The 2011 Seal Coat area includes the Loveland area from CR 30 north to CR 40. Informational signs will be posted on affected roads detailing exact locations and time frames. Our seal coat program differs from the chip seal program in that a very light coat of sand is applied after the sealing coat and no rocks are applied to the road surface. Please call our Seal Coat project line at 498-5666 or visit our web page for schedule updates.
Traffic will be limited to one lane in these
areas, expect delays of 10-15 minutes. Motorists, bike riders and pedestrians may
wish to choose alternate routes until the work is completed, usually no later
than 48 hours after product application.
We encourage all traffic to drive slowly through the work zones and obey
the posted speed limit to prevent materials that are being applied to the road
from getting on vehicles.
Roads
are listed in the order in which the work is expected to be completed. Informational
signs will be posted on affected roads detailing exact locations and time
frames.