Dream Lake iced over - RMNP
closure

County Offices and Courts will be closed on Monday, February 15, 2016 in observance of the President's Day Holiday. The Landfill will be open. Critical services at Larimer County are not disrupted by closures.

 
> Departments > Engineering > Capital Projects > Project Summary

BUCKHORN ROAD FLOOD DAMAGE REPAIR UNDERWAY

Project Number 9323
County Road 27 (Buckhorn Road) Flood Repair

Last Updated: November 18, 2015


SCOPE OF WORK

The Buckhorn Canyon Road (AKA County Road 27) sustained a great deal of damage from the 2013 floods. Three new bridges were constructed, one existing bridge was repaired, and 1.8 miles of roadway through the "Narrows" were reconstructed. To accomplish the above work approximately 40,000 cubic yards of rock were blasted and excavated, 30,000 cubic yards of riprap was placed, 11,000 tons of base course and 10,000 tons of asphalt were placed, and 2000 cubic yards of concrete were poured.

PROJECT STATUS

Construction work is now complete and all portions are open to traffic in both directions.

CONTACT

Matt Johnson, Project Manager
(970) 498-5724
Send e-mail



Engineering Home Previous Page

Background Image: Dream Lake frozen over in Rocky Mountain National Park by Bryce Bradford. All rights reserved.