LOAD POSTED COUNTY ROAD 18 CULVERT TO BE REPLACED

Project Number 312
(Replacement of Structure No. 18-0.4-23E)

Last Updated: December 16, 2015

SCOPE OF WORK

Replace the load posted metal box culvert on County Road 18 at the Handy Ditch, 0.4 miles east of County Road 23E.

Project Budget: $250,000

PROJECT STATUS

Preliminary plans complete. Construction now tentatively scheduled for fall 2017.

CONTACT

Joe Temple, Project Manager
(970) 498-5717
Send e-mail