> Departments > Engineering > Capital Projects > Project Summary

WILLOX LANE (CR 50) REPLACEMENT IN DESIGN

Project Number 310
(Replacement of Bridge No. 50-0.2-17 Over the Larimer and Weld Canal)

Last Updated: August 19, 2014

SCOPE OF WORK

The project includes the replacement of this deteriorating concrete and steel bridge on Willox Lane over the Larimer and Weld Canal just north of Fort Collins. Approximately 600 feet of roadway east and west of the bridge (1,200 feet total) will be reconstructed with the project. AECOM has been selected as the design consultant. Construction is currently scheduled for January through April of 2016 due to a rescheduling of the North Shields Street Corridor project construction (PN 301) in 2015. This project is funded through a federal bridge grant.

Project Budget: $1,100,000

PROJECT STATUS

The final design is complete. Right of Way acquisition and utility relocation coordination are underway.

CONTACT

Ron Winne, Project Manager
(970) 498-5713
Send e-mail