Mariana Butte Golf Course
 
> Departments > Engineering > Capital Projects > Project Summary

BRIDGE REPLACEMENT & ROAD RECONSTRUCTION PLANNED ON COUNTY ROAD 17

Project Number 301
(Replacement of Bridge No. 17-0.5-48 over the Poudre River & Road Reconstruction of N Shields from the Arthur Ditch to Willox Lane)

Last Updated: May 15, 2015

SCOPE OF WORK

North Shields (County Road 17) is a major arterial connection between Fort Collins and northern portions of unincorporated Larimer County. It is often utilized by regional traffic from / to US 287. The corridor is also a major access point for the regional Poudre River Trail.

This narrow, 2-lane roadway carries more than 9,000 vehicles per day without turn lanes for accesses, adequate shoulders, bike lanes, or pedestrian facilities. The access to the Poudre River Trail is ill-defined without dedicated parking or bike/pedestrian facilities. There are more than 30 access points along the corridor in less than one mile. There have been 21 crashes in the corridor in the last 5 years, including 4 in 2010. The project goal is to separate the various modes of travel (vehicles, bikes, and pedestrians) and provide a refuge for turning vehicles. The details of the improvements have not yet been identified.

Larimer County has applied for and received three federal grants to make improvements to this segment of North Shields. One grant is to replace the bridge over the Poudre River, another is to make improvements to Shields Street between the Arthur Ditch and Willox Lane and the third is to provide an area for a trailhead/parking area for the Poudre River Trail. Further information on this project can be found on the project web page.


Project Budget: $7,100,000


PROJECT STATUS

Construction is in full swing. City of Fort Collins crews began work in early December on the installation of a new sewer main and future electric/communications duct bank running north from Vine to Willox street.

Duran Excavating is performing the bridge and road construction for Larimer County. Their crews began work on February 2nd. The river bridge foundation caissons, abutments, and pier columns are complete and girders have been erected. The Arthur Ditch concrete box culvert is complete except for parrapet walls, railing and sidewalk. Roadway construction south of the river is also underway. Utility new construction and relocation work continues along the length of the project.

The County is excited about the start of this project and look for a completion in August.

CONTACT

Ron Winne, Project Manager
(970) 498-5713
Send e-mail



Engineering Home Previous Page

Background Image: Mariana Butte Golf Course by Steve Moore. All rights reserved.