> Departments > Engineering > Capital Projects > Project Summary

NEW NORTHERN EXTENSION AND ROUNDABOUT FOR OWL CANYON ROAD (CR 19

Project Number 288
(County Road 19 from County Road 70 to County Road 72)

Last Updated: June 16, 2014


SCOPE OF WORK

Construct a new roadway from the CR 19 / CR 70 intersection northwest to the CR 21 / CR 72 intersection. A roundabout will be constructed approximately 150 feet west of the CR 19 / CR 70 intersection. The roadway will be paved to a 40 foot width (two 12' lanes + 8' shoulders). CR 70 west of CR 19 and CR 21 between CR 70 and CR 72 will become private roads after project completion.

Project Budget: $5,000,000

PROJECT STATUS

Connell Resources has begun construction. They have been given until October 31, 2014 to complete the work.

County Road 72 will be closed between Latigo Way (west of CR 17) and CR 21 with a detour to CR 70 until late July.

CONTACT

Joe Temple, Project Manager
(970) 498-5717
Send e-mail